This schedule was last updated on 28th May 2009. Each major feature area has a list of tasks and associated schedule.

Features

Feature Priority Time estimate (minimum) Percentage done
Network stack Top 3 months 15%
Linux driver layer (for network drivers only) High 1 month 35%
ATi and NVidia 2D drivers for Xynth High 1 month 0%
Package management Mid 1 month 0%

Schedule

Date Milestone Features
August 31 2009 0.3-alpha Network stack in usable state, Linux driver layer can run several network drivers, ATi and Nvidia drivers can change to desired resolution
September (on holiday)
October 15 2009 0.3-beta Review process, possible alpha of package manager
November 1 2009 0.3 (and release candidate series) Package manager in stable state